Stork Gears & Services Stork Gears & Services
Stork Gears & Services English Portuguese
Home  > Products & Services  >  Gearbox diagnostics  >  Testing plants
Search this website
Stork
StorkGearbox repair
StorkGearbox maintenance
StorkOptimization services
StorkGearbox alignment
StorkCustom-built gearboxes
StorkEquipment management

Stork Gearbox Emergency contact

Gearbox monitoring
24 hours a day
Live showcase »

Testing plant

An important last step in the overhaul process is the trial run of an overhauled idling gearbox on our testing plant. This testing plant is an area of 60 m2 where our trial run procedure can be run through with 5 gearboxes simultaneously.

It is possible to test up to a power of 187 kW and a rpm of approx. 20,000. These high rpms are attained using a "speed-up" gearbox. The gearbox is operated for 4 hours during this procedure, in which the following parameters can be analysed:
  • Temperature
  • Vibrations
  • Noise
  • Oil viscosity
All testing data is recorded in a test report, which will be sent to the client and filed by us.
Testing plant